Renovation work on the sports area in Parque de Poniente in Villanueva de la Cañada, Madrid


Renovation work on the sports area in Parque de Poniente in Villanueva de la Cañada, Madrid

Expansion of the sports area of Parque de Poniente in Villanueva de la Cañada with the construction of a new skate park and the improvement of the current facilities.

Client:
Villanueva de la Cañada Town Council
Location:
Madrid
Period:
2022-2023
Type of service:
Public roads and signage
The project is intended to renovate and extend the sports area of Parque de Poniente in the Madrid municipality of Villanueva de la Cañada. With the remodelling of the existing skate plaza, the area will be used to create a skate park and a new bowl, extending the paved surface.
The new sports equipment is intended to be more visible and to attract more skaters.
 
The following noteworthy work was carried out:
• Paving of the new skating surfaces with polished concrete.
• Paving of the accesses to the skate area in ceramic paving stones.
• Installation of new street furniture with litter bins, benches, fountain, etc.
• Installation of a perimeter railing on the converted skate park for the viewing area, which is accessed by a clinker brick pathway, framed under metal yellow arches.
• Lighting with 10 m high poles and directional spotlights.
• Planting of shrub species in areas around the perimeter of the skating area and planting of flower beds in mounds located inside the skating area.
• Installation of a drip irrigation network.
• Installation of a sewerage network.
 
DETAILS

Technical data

Refurbishment and structure

· 462 m² removal of metal fence.
· 9 m³ demolition of brick wall.
· 58 m²demolition of concrete slab.
·714 m³ of gravel aggregate for the base and elevated elements.
·  2,754 m² of land clearing and cleaning.
- 5,284 kg of steel structure.
·  12 m³ cleaning concrete HM20.
- 24 m³ reinforced concrete HA 25.

Paving and paint

· 1,157 m² polished concrete HA25.
· 895 m² continuous concrete paving HAD-400
· 142 m² clinker bricks
· 246 ml kerbstone (bush-hammered granite and concrete)
· 11 m² coloured button tiles and 19 m² grey 4-block tiles. 
· 894 m² varnishing polished areas.
· 431 m² acrylic paint.
· 166 m² matt synthetic enamel and 147 m² thermoplastic paint.

Equipment and lighting

· Six tube benches.
· Six circular steel litter bins.
· Model FH-01 steel fountain.
· Galvanised steel bicycle parking area.

Equipment and lighting

· 22 Clear Flood LED floodlights 265 W - 42,000 lm.
· Seven 10 m high ETO model truncated cone light columns.

Landscaping, irrigation and sanitation

· 100 m² of flower beds and 35 m³ of mulch.
· 2,118 planting of various shrub species.
· 5,250 ml of drip irrigation pipe.
· 14 plastic inspection chambers and 20 brickwork inspection chambers.
· 95 ml of DN200 PVC pipe and 48 ml of DN250 PVC pipe.
· Two manholes and seven brickwork catch basins.

Downloads


Gallery